OWNER: The Robstown Independent School District (RISD)

ARCHITECT: Gignac & Associates (361) 884-2661

GENERAL CONTRACTORS: The DLP Group, Art Campos (361) 857-5050

PROJECT COST: $1,950,000.00

START DATE: November 2017 / COMPLETION DATE: March 2018

PROJECT DESCRIPTION: The Robstown Early College High School Phase II project included the renovation of a 39,000 sq. ft. campus. The interior renovations included new vinyl flooring or carpet, paint, baseboards, ceiling tiles, and new LED lighting. The exterior renovations included patch work, new paint, and new exterior lighting to the existing administration building, concrete canopies, and cafeteria. The existing parking lot was patched and re-striped.

SCOPE OF WORK: General Contractor. Furnish all material and labor for the completion of the project.