DR. CLOTILDE P. GARCIA PUBLIC LIBRARY

OWNER: The City of Corpus Christi

ARCHITECT: WKMC Architects

GENERAL CONTRACTORS: The DLP Group

PROJECT COST: $2,910,550.00

START DATE: October 2007 / COMPLETION DATE: December 2008

PROJECT DESCRIPTION: Design-build of a new 15,000 SF library with children’s area, computer work area, and research areas included within.

SCOPE OF WORK: General Contractor. Furnish all materials and labor for the completion of the project. Self-performed interior and exterior finish-outs.

 

 

 

ORNL CLO AUDITORIUM

OWNER: Department of Energy, Oak Ridge National Laboratory

ARCHITECT: KZF Design

GENERAL CONTRACTORS: The DLP Group

CONTRACT AMOUNT: $2,400,000.00

START DATE: October 2005 / COMPLETION DATE: May 2006

PROJECT DESCRIPTION: Design-Build of a new auditorium including seating, mill-work, and a audio visual infrastructure.

SCOPE OF WORK: General Contractor. Furnish all materials and labor for the completion of the project.

 

 

 

Shell Mars B Living Quarters Module

OWNER: Royal Dutch Shell

ARCHITECT: Shell Engineering

GENERAL CONTRACTORS: Broadmoor

PROJECT COST: $93,200,500.00

START DATE: October 2012 / COMPLETION DATE: June 2013

PROJECT DESCRIPTION: Shell’s offshore platform living quarters module, a four-story living quarters to 192 people which features kitchens, fitness rooms, control rooms, and an on-site medical facility.

SCOPE OF WORK: Subcontractor. Interior finish outs.

 

Early Childhood Development Center at Ft. Bliss

OWNER: US Army Corp Of Engineers

ARCHITECT: Megen Construction, Inc.

GENERAL CONTRACTORS: The DLP Group

PROJECT COST: $17,160,000.00

START DATE: July 2009 / COMPLETION DATE: February 2010

PROJECT DESCRIPTION: 26,450 SF facilities for ages 0-5, which include pre-school and toddler rooms, training spaces, administrative offices, and a full kitchen.

SCOPE OF WORK: Subcontractor. Divisions 051000 Metal Framing, 071900 Water Repellents, 099113 Painting, & 099600 Special Coatings.

 

 

 

North Ft. Hood Firestation

OWNER: Department of Army, Ft. Worth Corps of Engineers

ARCHITECT: KZF Design

GENERAL CONTRACTORS: The DLP Group

CONTRACT AMOUNT: $4,797,024.00

START DATE: October 2006 / COMPLETION DATE: October 2007

PROJECT DESCRIPTION: Design-Build of a new 15,000 SF fire station.

SCOPE OF WORK: General Contractor. Furnish all materials and labor for project.

Demo Buildings 2700, 3729, & Remodel Building 3730 at Naval Air Station Kingsville

OWNER: Department of Navy / NAVFAC

ARCHITECT: KZF Design

GENERAL CONTRACTORS: The DLP Group

PROJECT COST: $2,455,500.00

START DATE: April 2009 / COMPLETION DATE: July 2010

PROJECT DESCRIPTION: Renovation of one (1) building, demolition of one (1) three-story building, and a partial demolition to one (1) single story barracks.

SCOPE OF WORK: General Contractor. Furnish all materials and labor for project. Self performed interior finish-outs.